Table of Contents Table of Contents
Previous Page  34 / 92 Next Page
Information
Show Menu
Previous Page 34 / 92 Next Page
Page Background

32 Independence Group NL

CONSUMABLES

The main consumables at the mine are diesel, lime,

cyanide, carbon and water.

An on-site diesel-fuelled power station provides 40 MW

installed capacity. APA Group is currently constructing a

pipeline from Murrin Murrin to Tropicana to deliver gas.

Once complete, the existing diesel generators will be

replaced with gas-fired generators and so reduce both cost

of operation and the mass of emissions.

Relatively little water enters the pit voids from

groundwater seepage or rainfall. Water is supplied by

borefields, which are used to extract water from nearby

aquifers. In the 2014 calendar year a total of 4,362,473 kL

was abstracted from the process water supply bore field

plus an additional 532,488 kL which was abstracted from

operational bores. At stages during FY2015 the processing

facility was constrained due to a lack of water. This

occurred because there was a lower than predicted level

of water available from existing borefields; a lower than

predicted level of water in the open pits; and periods of

intensive water usage during construction of the tailing

storage facility. Water security has recently been achieved

by drilling additional bores. Water from the tailings storage

facility is recovered and recycled.

WASTE

The key waste streams from the mine are waste rock and

tailings. In addition to the gold bearing ore, waste rock is

extracted from the various pits. This rock (predominantly

ferrunginous cherts) contains some material that is

classified as potentially acid forming (PAF). Such material,

if left unmanaged and exposed to the elements, can

generate an acidic discharge that can cause downstream

impacts on biota and groundwater. Given this, the waste

rock dumps have been designed and are being constructed

to ensure the PAF material is blended with the neutralising

waste rock. This combined material is placed away from

what will be the final slopes of the waste rock landform.

Tailings are a thick water-based suspension of fine

crushed rock, sand, and clay produced from the

processing plant once the gold has been recovered. This

waste is pumped to the tailings storage facility, which is

designed to allow the tailings to settle and form a ‘beach’

that drains to a central pond. Ponded tailings liquor is

recovered and returned to the processing plant. Tailings

are cyclically deposited so the beaches evaporatively dry

and enable the dried tailings to be progressively stacked

higher. A key environmental consideration in this part

of the process is the presence of weak acid dissociable

cyanide in the tailings liquor.

The project development has required the clearance of

2,451 ha of natural bush to date. This includes both

mining and exploration disturbance but excludes open pit

disturbance.

A small volume of both putrescible and hard waste is

disposed of in the onsite landfill.

NATIVE TITLE

The Tropicana Gold Mine is wholly within the area of the

former Wongatha Native Title Claim (WC99/001). While

this claim was dismissed by the Federal Court in 2007,

AngloGold Ashanti continues to work closely with the

claimant group and other interested parties.

The most substantive nearby Aboriginal communities are

located at Laverton and Cosmo Newberry, both of which

are approximately 220km west-north-west of the site;

Coonana, which is approximately 225km south-west; and

Tjuntjuntjarra, 250km to the east. There are no pastoral

land holdings within the project area.

LIFE OF MINE

At present the expected life of mine for the mine is eight

years, based on current reserves. A mine closure plan has

been developed and is updated every three years.

A WA School of Mines graduate (BEng Mining

Engineering) with 3.5 years industry experience.

Having finishing his degree David started work as

an underground truck driver in 2012 and went on to

complete his introductory time underground including

in a variety of roles like nippering, service crew,

charge up, bogging and long hole drilling.

“I like my job not just because this is what I

want to do, but because the people I work

with really look after each other. As a mining

engineer, there are many challenging tasks

such as drill and blast design, magazine

management, and weekly scheduling to

name a few … it is all a good opportunity to

learn.”

Yingpeng (David) Wei

Mining Engineer

Jaguar Operation