42 Independence Group NL

NOVA PROJECT

The Nova Project is based on a twin nickel-copper-cobalt

sulphide deposit known as the Nova-Bollinger deposit.

The Nova-Bollinger deposit is 700km east of Perth. Sirius

Resources NL (Sirius) obtained 100% ownership in May

2014 following the purchase of Mark Creasy’s 30% joint

venture interest.

A Definitive Feasibility Study (DFS) was completed on

14 June 2014. As part of the DFS, the Nova-Bollinger JORC

resource estimate was updated to 14.3 Mt at 2.3% nickel,

0.9% copper and 0.08% cobalt for 325,000 tonnes of nickel,

134,000 tonnes of copper and 11,000 tonnes of cobalt.

On 4 August 2014, Sirius signed the Nova Mining

Agreement with the Ngadju, the traditional owners of the

land comprising the Nova Project. Subsequently, the Nova

Mining Lease (M28/276) was granted on 19 August 2014.

Construction at Nova commenced on 26 January 2015,

following receipt of final statutory approvals.

At full production, Nova is expected to produce an

average of 26,000 tonnes of nickel, 850 tonnes of cobalt

and 11,500 tonnes of copper annually. On 27 February

2015, it was announced that a three-year off-take

agreement had been signed with BHPB for 50% of the

forecast nickel sulphide concentrate to be produced from

Nova. Subsequently, on 13 May 2015 Sirius announced it

had signed a three-year off-take agreement with Trafigura

for 100% of its future copper sulphide concentrate

produced from Nova.

Milestone

Estimated

Timing

First Ore from Development

Q2 2016

First Ore Feed to the Processing Plant

Q3 2016

First Concentrate Production

Q4 2016

First Nickel Concentrate Shipment

Q1 2017

First Copper Concentrate Shipment

Q1 2017

In January 2015, following the granting of all mining

permits, excavation and construction of the interim

accommodation, aerodrome and access road commenced.

A 492-person accommodation village has been largely

completed and the initial construction camp has been

decommissioned. A 2km long, all-weather, sealed airstrip

has been completed as has the tailings storage facility.

The underground mine’s box cut was completed in May

2015 and the development of the decline is progressing

to plan.

In June 2015, GR Engineering Services Limited was

awarded a $114 million Engineering, Procurement

and Construction (EP&C) contract for the design and

processing of the mineral processing and paste fill plant.

Design work on the plant is underway and expected to be

completed in November 2016.

Production from the Nova Project is expected to

commence in late 2016.

14.3 Mt

nickel ore mineral resource