OPERATIONAL SCORECARD AND OUTLOOK

FY17 GUIDANCE (Compared to FY16 guidance and performance)

Mining Operation

Units

FY16 Guidance Range

(1)

FY16 Results

FY17 Guidance Range

Tropicana (IGO 30%)

Gold produced (100% basis)

oz

430,000 to 470,000

448,116

390,000 to 430,000

Gold (IGO’s 30% share)

oz

129,000 to 141,000

134,435

117,000 to 129,000

(2)

Cash cost

A$/oz Au

680 to 750

730

850 to 950

All-in Sustaining Costs

A$/oz Au

900 to 950

918

1,150 to 1,250

Sustaining capex

A$M

14 to 16

6.4

2 to 3

Improvement capex

A$M

See Note 4

5.9

2 to 3

Capitalised waste stripping

A$M

18 to 20

16.1

29 to 36

Exploration expenditure

A$M

9 to 11

7.6

6 to 8

Long

Nickel (contained metal)

tonnes

8,500 to 9,000

8,483

7,400 to 8,200

Cash cost (payable)

A$/Ib Ni

3.50 to 4.00

3.68

3.50 to 3.90

Sustaining capex

A$M

2 to 3

1.7

1

Exploration expenditure

A$M

8 to 9

7.1

2 to 3

Jaguar

Zinc in concentrate

tonnes

38,000 to 40,000

39,335

39,000 to 43,000

Copper in concentrate

tonnes

6,500 to 7,000

7,412

4,600 to 5,100

Cash cost (payable)

A$/Ib Zn

0.60 to 0.70

0.53

0.70 to 0.80

Sustaining capex

A$M

2 to 3

1.8

8 to 9

Development capex

A$M

11 to 13

12.8

12 to 13

Exploration expenditure

A$M

9 to 10

8.9

3 to 4

Nova

Nickel in concentrate

tonnes

9,000 to 10,000

Copper in concentrate

tonnes

3,900 to 4,400

Cash cost (payable)

A$/Ib Ni

4.00 to 4.50

(3)

Capital Build capex (cash basis)

A$M

242

140 to 150

Sustaining capex

A$M

3 to 5

Development capex

A$M

22 to 25

Exploration expenditure

A$M

3.5 to 4.5

Greenfields & generative

A$M

6 to 8

6

11 to 15

1.

As restated in the March 2016 Quarterly Report

2.

Total gold hedging in FY17 represents 70% of guidance production including 72,600 ounces at A$1,641/oz

3.

Nova cash cost guidance for FY17 is indicative of the period of ramp-up following plant commissioning

4.

Improvement capex included in Sustaining capex for FY16 Guidance Range