18 Independence Group NL

Location

160km by road, east of Norseman

As at June 2016, the overall

Project was 93% complete

and was on schedule and on

budget to produce first nickel

and copper concentrates by

December 2016 as planned.

FY16 Production

n/a - in construction

Product

Nickel and copper

Resources

325,000t contained nickel and

134,000t copper

1

Mining

Owner operated underground mine

and process plant

Processing method

Conventional crushing, grinding,

flotation and filtration

Reserves

275,000t contained nickel and

112,000t copper

1

Sales

100% of nickel sulphide concentrate

for first three years have been signed

with BHP Billiton Nickel West Pty Ltd

and Glencore International AG. 100%

of copper sulphide concentrate for

first three years has been signed

with Trafigura Pte Ltd.

NOVA PROJECT - KEY MILESTONES

The Nova Project has progressed rapidly in 2016 which is a testament to the quality of the Project

and the commitment of all stakeholders involved in the Project.

1

See Resources and Reserves section

on pages 23-28 of this report

Discovery

Jul 2012

2012

2013

2014

2015

Scoping

Study

Sep 2013

Native Title

Agreement &

Mining Lease

Aug 2014

Maiden

Resource

May 2013

Definitive

Feasibility Study

Jul 2014

Permitting &

Construction

commencement

Jan 2015

Optimisation

Study

Dec 2015

Accelerated

Bollinger Decline

July 2016

IGO

acquisition

Sep 2015

Commissioning &

first concentrate

Dec 2016

2016

NOVA