OPERATIONS - NOVA PROJECT

FY17 will be both challenging and rewarding

as we complete the construction phase, move

through the commissioning phase and into

full operations

BACKGROUND

The Nova discovery hole was drilled in

July 2012 and a maiden resource was

released some 12 months later in May

2013. The current JORC 2012 compliant

Mineral Resource

1

is 14.3Mt 2.3%Ni,

0.9%Cu and 0.08%Co. The Definitive

Feasibility Study, completed in July 2014,

confirmed the robustness of the Project

and development at Nova commenced

on 26 January 2015. IGO acquired the

Nova Project in September 2015 through

the acquisition of Sirius Resources NL.

As at June 2016, the overall Project was

93% complete and was on schedule and

on budget to produce first nickel and

copper concentrates by December 2016

as planned.

CONSTRUCTION

Construction of the process plant and

its associated infrastructure was 86%

complete as at 30 June 2016 and was

being progressed ahead of schedule. All

major mechanical equipment was onsite

with the focus on piping and electrical

installation. It is expected commissioning

will commence in the December 2016

quarter with first saleable concentrate

produced in accordance with plan by

December 2016.

Other sections of the Project completed

to date include the 492 room

accommodation village, the 38km sealed

site access road, the sealed aerodrome

(certified for jet aircraft), the central water

treatment plant, the administration

facilities, the heavy equipment workshop

and associated fuelling and wash down

facilities and the life of mine tailings

facility.

Electric power for the Project is provided

by Zenith Pacific under a Build Own

Operate contract. Stage 1 of this power

generation facility, consisting of three

1.7MW diesel generators, has been

commissioned and is suppling reticulated

power to all areas of the Project. Stage

2, consisting of five 3MW GE diesel

generators, which are capable of

operating on either gas or diesel in the

future if required, will be commissioned

during the September 2016 quarter.

To supplement power generation at

Nova a 6.7MW solar farm is planned for

installation later in FY17.

The Project is expected to be completed

within the capital expenditure budget of

$443M and, with the work completed to

date, the risk of a capital cost overrun has

largely been eliminated.

$443

million

Capital Budget

492

room

Accommodation

Village

1st

Ore

June 2016