Table of Contents Table of Contents
Previous Page  17 / 128 Next Page
Information
Show Menu
Previous Page 17 / 128 Next Page
Page Background

Annual Report 2016 15

BACKGROUND

IGO targeted and pegged the area

containing the current gold reserves in

2001. AngloGold Ashanti farmed into

the project in 2002, discovering the

Tropicana, Havana and Boston Shaker

gold deposits respectively in 2005, 2006

and 2010. Mining of the Havana deposit

commenced in 2012 with the first gold

being produced in September 2013. In

October 2016, the Tropicana Gold Mine

achieved its 1 million ounce milestone,

in line with expectations outlined in the

2010 Bankable Feasibility Study.

FY16 PRODUCTION

Tropicana gold production for FY16 was

in line with expectation at 448,116oz (on

a 100% basis) and cash costs and All-in

Sustaining Costs (AISC) were $730/oz

produced and $918/oz sold respectively.

During the year, a total of 24.6M bank

cubic metres of material were mined and

hauled ex-pit. This material comprised

of 7.3Mt of full grade ore (>0.6g/t), 1.2Mt

of marginal ore (grading between 0.4 &

0.6g/t Au) and 50.3Mt of waste material.

Full grade ore sources were the Havana

Pit (4.47Mt), the Boston Shaker Pit

(0.82Mt) and Tropicana (2.0Mt) with the

average run-of-mine grade for full grade

ore (>0.6g/t Au) being 2.13g/t Au for the

year.

A total of 6.53Mt of ore at an average

grade of 2.39g/t Au was processed

during the year. Average metallurgical

recovery was 89% for 448,116oz of gold

produced.

The reduction in gold production for the

year compared to the FY15 (496,413oz)

is a result of the cessation of grade

streaming in December 2015. Gold

production is forecast to trend to long

term guidance of 400,000oz/pa once

expansion of the process plant to 7.5Mtpa

is achieved.

ATTRIBUTABLE PRODUCTION

IGO’s attributable gold production

during FY16 was 134,435oz and IGO’s

attributable share of gold refined and

sold was 135,864oz. IGO’s attributable

average cash costs for FY16 were $730/

oz Au produced and AISC were $918/oz

Au refined.

TROPICANA OPTIMISATION PROJECT

Business improvement initiatives

within the mining operation include the

implementation of priority road rules,

which have improved mining costs

and efficiencies by reducing haul truck

stoppage time.

Optimisation and upgrade of the process

plant due for completion in September

2016 is targeted to achieve a throughput

rate of 7.5Mtpa. This project involves

optimisation and upgrade of existing

equipment including:-

Upgrades to the conveyor systems in

the secondary crushing, High Pressure

Grinding Rolls (HPGR), and grinding

circuits

Optimising screens in the secondary

and HPGR circuits

Upgrade to the lime storage

Upgrade to the oxygen plant

Upgrade to the air water and elution

systems

Upgrade to the emergency fine ore

stockpile

Improved utilisation of the HPGR circuit

The progress of these works enabled the

process plant to achieve an annualised

rate of 6.88Mtpa in the June 2016 quarter

at a 95% availability with May and June

achieving an annualised rate of 7.3Mtpa.

GAS PIPELINE PROJECT UPDATE

The gas pipeline project including the

installation of the gas fired generators is

complete with the commissioning of the

17 gas fired generating units. Further cost

savings resulting from this project will

be achieved as site equipment requiring

LNG as fuel is progressively upgraded to

operate on natural gas.

LONG ISLAND STUDY

The Long Island study is looking at

alternative lower cost mining methods

to enable the mining of ore below the

currently planned pits.

This approach is considering strip mining

mine design techniques, more commonly

used in the coal mining industry which

has the effect of reducing haulage of

waste as the open pit mining progresses

at depth. The concept involves the

existing Tropicana pit, once its resources

are depleted, being backfilled with waste

from the strip mining of the Havana,

Havana South, and Boston Shaker ore

zones. This approach would reduce

waste removal costs as a result of in

pit dumping of waste and shorter haul

distances which would, in turn, facilitate

the extension of mine life.

The study is supported by data from a

substantial framework drilling program

targeting extensions beneath and along

strike of the existing pits completed

during FY16.

OPERATIONS - TROPICANA GOLD MINE

IGO 30%, ANGLOGOLD ASHANTI 70% (MANAGER)