Annual Report 2016 21

THE YEAR AHEAD

FY17 will be both challenging and rewarding

as the construction phase is completed,

followed by the commissioning phase

and into full operations. Commissioning

is expected to begin in earnest in the

December 2016 quarter and for first

concentrate to be produced in December

2016. Ramp up to full production is expected

to be complete by June 2017.

The project is expected to be

completed within the capital

expenditure budget